Repair & Maintain Building 204, Stewart Air National Guard, Newburgh, NY


Brief Project Description:

Work performed under this contract included but was not limited to:

The complete overhaul of the HVAC system:

• Conversion of Pneumatic system to Direct Digital Controls (DDC).

• Up Grade all VAV (eliminate all pneumatics to them).

• Up Grade/Repair All Air Handling Units.

• Up Grade/Repair All Air Conditioning Units.

• Up Grade Supply and Return Registers.

• Redesign of the fin tube heating, to ensure adequate sizing.

• Up Grade/Repair Boiler.

• Upgrade fire suppression system throughout the building.

• Repair lavatories to include new upgrades to equipment and ventilation systems.

• Repair damaged/cracked flooring in warehouse.

• Repair roll‐up door in warehouse to install observation windows in the doors.

• Make necessary repairs to damaged walls (gypsum board), ceiling tiles and floor coverings.

• Seal building envelope (water repellent protection to the exterior block).

• Upgrade/Repair lighting in warehouse area.

• Upgrade break area next to main conference area.

• Enclose overhangs on east side of building.

• Evaluate adding circuits to the back‐up generator.

• Up Grade office space and common areas cosmetically (paint, floor coverings).

This project reflects Benaka Inc.’s experience in multi trade coordination.

Contract Value:

$2,654,000

Client:

Stewart Air Force Base, Newburg, NY

Project Completion:

June 2011