Water Intrusion Repairs, USCG - Fort Wadsworth, Staten Island, NY


Brief Project Description:

A summary of the work on the Water Intrusion Repairs USCG Staten Island includes:

• Removal/Replacement of brick veneer to correct deficiencies with hangers, expansion joints, angles, flashing and brick replacement.

• Remove/Replace existing light commercial grade double-hung aluminum windows with heavy-duty impact-resistant double-hung aluminum windows.

• Remove and replace all exterior hollow metal doors, and interior non-compliant door HW.

• Removal and installation of low-sloped roofs at entrance and re-entrant corners (EPDM roofing system, metal cap flashing, tapered rigid insulation, protection board, new thru-wall flashing at cavity walls).

• Remove/Replace all brick veneer expansion joint sealant.

• Gypsum board repairs as required for plumbing and electrical repairs.

Contract Value:

$2,140,000

Client:

Fort Wadsworth, Staten Island, NY

Project Completion:

June 2014